They seem to put these out quarterly and there's always something new in there. I'll try to keep this updated when I notice they've posted a new one.
Here's the most recent one as of 15-December.
Highlights:
The chemistry building is 26% complete. Here are some pictures from their website:
The Engineering building (104000sqft) is still going through design and will be done in Summer 2018
They are adding a third floor to the Waksman Institute for $6M and an additional 7410sqft
The Pharmacy Building addition will be done in Fall 2017 and add 5700sqft